Registration/Renewal Timeline unde all Acts
Click here to view Notification
|
Name of Acts
|
Timeline (Mandated by Department)
|
Rajasthan Shops & Commercial Establishments Act, 1958
|
Timeline for Application Disposal For Registration:-
1 day from the date of submission of complete application alongwith requisite fee and documents.
For Renewal:-
1 day from the date of submission of complete application alongwith requisite fee and documents.
|
The Contract Labour (Regulation and Abolition) Act, 1970 (Contractor)
|
Timeline for Application Disposal For Registration:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
For Renewal:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
|
The Contract Labour (Regulation and Abolition) Act, 1970 (Principal Employer)
|
Timeline for Application Disposal For Registration:-
30 days from the date of submission of complete application alongwith requisite fee and documents.
|
Building And Other Construction Worker’s (RE & CS) Act, 1996
|
Timeline for Application Disposal For Registration:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
|
Trade Unions Act, 1926
|
Timeline for Application Disposal For Registration:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
|
The Beedi And Cigar Workers (Condition of Employment) Act, 1966
|
Timeline for Application Disposal For Registration:-
10 days from the date of submission of complete application alongwith requisite fee and documents.
For Renewal:-
10 days from the date of submission of complete application alongwith requisite fee and documents.
|
Motor Transport Workers Act, 1961
|
Timeline for Application Disposal For Registration:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
For Renewal:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
|
The Inter-State Migrant Workmen (RE & CS) Act, 1979 (Contractor)
|
Timeline for Application Disposal For Registration:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
For Renewal:-
15 days from the date of submission of complete application alongwith requisite fee and documents.
|
The Inter-State Migrant Workmen (RE & CS) Act, 1979 (Principal Employer)
|
Timeline for Application Disposal For Registration:-
30 days from the date of submission of complete application alongwith requisite fee and documents.
|